Anggota Komisi IV DPR RI Riyono.|Foto : Naifuroji/MRI.
PARLEMENTARIA, Jakarta — Riyono, a member of Commission IV of the Indonesian House of Representatives (DPR RI), questioned whether the target of accelerating construction of a 575-kilometer giant sea wall, or Giant Sea Wall (GSW), along Java’s North Coast within 15 years was feasible. He said the strategic project, which requires nearly Rp700 trillion in investment, faces major challenges, particularly in financing, and therefore cannot rely solely on the State Budget (APBN).
Riyono made the remarks after attending a Commission IV hearing with the head of the North Java Coast Management Authority (BOPPJ) at Nusantara I Building, Parliament Complex, Senayan, Jakarta, on Thursday (19/11/2026). The first meeting with the new working partner discussed an introduction to its institutional structure and the BOPPJ’s 2027 Work Plan and Budget (RKA).
Riyono acknowledged the urgent need to build the GSW along Java’s North Coast to protect coastal areas from the threat of land subsidence and tidal flooding. These threats have even disrupted national logistics routes, including in the area of Pekalongan, Central Java.
However, he cautioned that accelerating construction by shortening the timeline from 20 years to 15 must be backed by careful planning—in terms of funding, implementation phases, and cross-sector coordination. Given the enormous investment required, the project’s financing scheme must also be designed realistically.
"The significant question is, in terms of the budget, I don’t think the state budget will be able to cover it. It will certainly require foreign loans or grants," Riyono said.
The Prosperous Justice Party (PKS) politician stressed that the 15-year completion target must be based on a comprehensive scientific study. He said the BOPPJ must ensure that the accelerated schedule is realistic and can be implemented without creating new problems on the ground.
"I’m issuing a warning: is 15 years enough? That’s the point I’m making," he stressed.
In addition to financing and the timeline, Riyono also emphasized the importance of strengthening nature-based coastal ecosystems before large-scale physical construction begins. One step he said should be prioritized is the rehabilitation and management of mangrove forests as part of efforts to protect coastal areas.
"I would actually favor building up nature-based ecosystem resilience first, before the physical construction—especially through mangroves. This is something the Giant Sea Wall management agency needs to pay attention to. Before construction, mangrove management must be prioritized," Riyono added.
For context, in its presentation of the 2027 Work Plan and Budget to Commission IV of the DPR RI, the BOPPJ proposed a budget ceiling of Rp481.11 billion, funded from domestic currency sources. The funds are allocated to support the operations of the agency, which is only 14 months old, and to carry out priority programs to prepare for construction of the GSW along Java’s North Coast.
The project is planned to extend 575 kilometers across five provinces. Preparatory activities include plans for initial groundbreaking ceremonies in Jakarta Bay and Semarang Bay, as well as arrangements for financing through Foreign Loans/Grants (PHLN) and Public-Private Partnerships (KPBU).
Through its oversight of the planning and budgeting process, Commission IV of the DPR RI is urging that construction of the GSW along Java’s North Coast focus not only on accelerating construction, but also on financing feasibility, environmental sustainability, and effective protection for coastal communities. (ndy/ssb)